Headlines

South Campus taking shape

Construction is progressing on the Goodman South Campus on the corner of Badger Road and Park Street and will be completed for the Fall 2019 academic year.

Projects currently underway on the 75,000-square-foot campus include:

  • Drywall finishing is complete and painting has begun on second floor.
  • MEP trades are doing finish work throughout the building.
  • Building finishes are ongoing throughout the building.
  • Curtain wall work is nearly complete on area B. A few pressure plates still need to
  • be installed.
  • Resilient flooring is being installed on the first and second floors.
  • Work is on going on the parking lots. Curbs and remaining sidewalks will begin next week.
  • Doors and hardware are being installed on the lower level.
  • Foundations have been poured for the large planters at the north entry.
  • Lab casework installation is on-going in the lower level.
  • The first load of classroom furniture is scheduled for delivery on 6-19-19 for the lower level.
  • Miron's overall project completion schedule shows August 25, 2019 as the substantial completion date. 

 

When completed, the campus will feature a brightly lit Café Servery and seating area, a library, a Student Achievement Center, flexible classrooms, a practical nursing lab, a chemistry lab and main service counter. The South Courtyard Entrance will feature a landscaped seating area, bicycle parking and vehicle parking.

For a complete list of programs that will be offered at the campus visit the Goodman South Campus page.

College transfer Arts and Sciences classes will also be taught there.

Two live webcams are recording the construction.

Camera 1: https://app.truelook.com/?u=mm1526503625

Camera 2: https://app.truelook.com/?u=mm1526503760

Visit the college SharePoint site for more information including PDFs and updates.

Contact Mike Stark with any questions.

Published May 22, 2019. Updated June 7, 2019.